Public Works and Environmental Services

CONTACT INFORMATION: Our offices are open to the public by appointment only at this time. Please call or email 8 a.m. - 4:30 p.m., Monday - Friday
703-324-5033 TTY 711
12000 Government Center Parkway
Suite 448 Fairfax, VA 22035
Christopher S. Herrington
Director

Long Branch Pump Station Replacement Project

Project Number: WW-0000001-049

Project Update: July 30, 2026


Project Background

Due to the age and condition of the existing pump station structure, the County is initiating a preliminary study to evaluate the option of replacing the current pump station with a new facility constructed on the same parcel.

Project Description

The scope of work for this project will include professional engineering services to develop the Long Branch Pump Station Replacement Preliminary Engineering Report (PER). The PER will identify feasible options to replace the Long Branch Pump Station at its existing site to ensure long-term reliability of the facility, with the new station connecting to the existing force main and gravity sewer. The PER will evaluate pump station configurations that improve operations, maintenance, and facilitate future rehabilitation. It will present viable alternatives and design recommendations based on lifecycle cost, constructability, and Fairfax County preferences. The results of this evaluation will guide final design decisions and operational strategies.

Project Location

8750 Telegraph Road, Lorton, VA 22079

Project Phase

Study phase

Project Benefits

  • Replacement of all pump station structural elements, excluding the forcemain and its vault.
  • Replacement of all architectural elements associated with the pump station.
  • Development of the site and pump station access to ensure the critical elements of the PS and its access are above 100YR. floodplain.
  • Replacement of all MEP elements associated with the pump station.
  • Replacement of all instrumentation elements associated with the pump station.

Timeline

The Preliminary Engineering Study began in spring 2026 and is anticipated to be completed by winter 2026.

Project Cost

The study Cost is $282,685

Contact

For more information, please email project manager Joseph Gerges at Joseph.gerges@fairfaxcounty.gov.