Wellington-Hollin Hall Neighborhood Stormwater Improvement Study (NSIS)
Project Number: SD-000032-173
Project Update: November 6, 2026
A study has started to check the stormwater pipes that run through the neighborhood. The County wants to understand how often flooding has happened and how likely it is to happen again. County workers and contractors are doing surveys and talking with residents about flooding problems and past flooding events. The study will continue until early 2028 and include opportunities for community members to talk about flooding experiences and possible solutions. Construction will not be completed at this time.
Wellington and Hollin Hall were built in the 1940s. Many of the homes are built on top of historic drainage paths and are served by a roughly 80-year-old stormwater system. These communities are being studied in response to reports of repetitive flooding. The area contributing to the local stormwater management system will be studied to better understand stormwater behavior and system performance. As a result of the study, the County hopes to find solutions for a sustainably stronger and more reliable stormwater management system that helps reduce flooding, protect homes, and support the community’s ability to recover long-term.
Project Description
In alignment with Fairfax County’s Flood Risk Reduction Policy, the Department of Public Works and Environmental Services, Stormwater Planning Division (SWPD), has partnered with GKY & Associates, WSP USA, and Triad Engineering to conduct a Neighborhood Stormwater Improvement Study (NSIS) in the Wellington and Hollin Hall community.
The main goals of the study are:
Assess the stormwater system’s function and identify flooding patterns.
Inform residents about ways to prepare for future flooding.
Develop community-informed recommendations to reduce flood risk.
The study team actions include:
Assess about 14,000 linear feet of underground stormwater pipes and associated structures and develop a computer model to show how stormwater moves through the study area.
Present findings on the stormwater system and flooding patterns and collaborate to find possible solutions.
Work with community members to learn about their experiences and determine the next steps to improve stormwater management and reduce flooding risk.
Project Location
The study is in Fairfax County, focused on the 213-acre drainage area located between Route 1 and the George Washington Memorial Parkway, just south of Belle Haven and north of Mount Vernon. The study area is outlined in black below.
Map showing the Wellington and Hollin Hall study area outlined with a solid black line. The study area, outlined in black, runs between Route 1 and the George Washington Memorial Parkway, just south of Belle Haven and north of Mount Vernon. The orange lines inside the study area show the location of private stormwater pipes or channels and blue lines show the locations of public stormwater pipes or channels. Individual properties are outlined in gray and street names are shown.
Project Phase
The study is currently in the phase where we collect data on the stormwater network. County staff and consultants are examining the stormwater pipes and flooding issues in the neighborhood. They will then build models of what they find and present them to the community. No decisions will be made about construction or next steps until after this study and conversations with the community are complete.
Project Benefits
The environmental benefits of the study are:
Understand how the stormwater system functions today.
Develop recommendations to mitigate future flood risk and support a long-lasting stormwater system.
Help residents prepare to protect their families and homes from flooding.
Timeline
The study will run through early 2028.
What To Expect
County and consultant staff will be doing field work in the Wellington and Hollin Hall community during the study. They will be walking, collecting data, and taking measurements and photos of outfalls, pipes, manholes, easements, and related facilities. Contractors may use tools with metal rods and equipment to help them inspect stormwater pipes and flooding areas. If county or consultant staff in the field need to access private properties, they will ask for verbal permission on the day access is needed.
The team will engage with residents throughout the study to learn about their experiences with stormwater and flooding in the study area, get their input, and share study results.
Project Cost and Funding Source
The Wellington and Hollin Hall study is funded at $992,000.
Money for future design and construction (such as repairing or replacing pipes or building new flood control features) is not yet guaranteed. It will depend on future county budgets and funding decisions. Stormwater studies like this are paid for through the county’s Stormwater Service District.