Land Development Services

CONTACT INFORMATION: Monday through Thursday, 8 a.m. - 4 p.m. and Friday, 9:15 a.m. - 4 p.m. Please note that visitors may not be added to in-person queues past 3:45 p.m.
703-222-0801 TTY 711
12055 Government Center Pkwy
Fairfax, VA 22035
Bill Hicks
Director

Bond Alterations

Bond Extensions

Once permits have been issued for a project, the developer must complete the public improvements by the date identified in the agreement.  If the work is incomplete by that date, a bond extension is required.

The developer of an incomplete project is notified 60 and 30 days prior to the expiration date.  If an extension is not submitted prior to the expiration date, the project is in default.

To begin the extension process, a Development Agreement Extension Request Form  and the appropriate fee must be submitted to the Bonds and Agreements Center.

View a chart of the Bond Extension process.

Staff reviews the extension request to ensure it is complete and consistent with the original agreement.  However, before an extension is granted for a third and subsequent extension requests, the county conducts research to determine if the project is likely to default.

Once complete, the extension package is submitted to the Bond Committee for approval.

Bond Reductions

Bond reductions are requested when a project developer seeks to decrease the original bond amount posted with the county, based on the work completed. Before submitting a reduction request, it is recommended that the developer and engineer conduct a site walk with the site inspector. Reductions will not be granted for projects less than 30% complete, and no bond will be reduced to an amount insufficient to cover total project completion, including the full original 10% contingency.  Each project is eligible for up to three reductions per year.

A current Surety Value Estimate (SVE) using the current year's Unit Price Schedule, showing the percentages of work completed for each listed item, must be submitted with the appropriate fee to the Bonds and Addressing Center for review. Reduction "milestones" exist for each section of the SVE, with criteria that must be met to receive a reduction. The submitting engineer should refer to the Reduction Milestone Guidelines before submitting the request.

Please note that each bonded project is unique, and the milestones provided are general guidelines. Some bonded items, such as proffered improvements, may not be eligible for reduction if they are not fully installed. Proffered improvements include, but are not limited to, bike racks, bus shelters, tot lots and landscaping. Not all projects will align with the percentage ranges listed. Final percentages are determined by the site inspector and may differ from the tables below. Also, as-built plans will receive 0% if the associated SAB or SAN record is not "approved" in PLUS.

Once the Reduction Request is submitted, the Bonds and Addressing Center will route it to the site inspector for review. The inspector will verify the completion percentage for each item on the SVE. Once the work is verified, the Bonds and Addressing Center will notify the developer of the reduction.  Please note that reductions will not be approved until Bonds and Addressing Center receives a revised bond (e.g., an amended letter of credit or verification certificate). Due to inflation since the original bond was posted, the remaining bonded items may exceed the original bond amount. In such cases, a reduction may not be possible; however, the county will not require the increased bond amount to be posted.

Bond reductions are often combined with extension requests. Please confirm with your site inspector if your project requires a simultaneous extension.

Reduction Milestone Guidelines

Reduction Percentage

Criteria

0%

  • Trench dewatering - associated storm run installation not yet complete (percentage will be given with the amount complete)
  • Site As-built (SAB) - not submitted, or approved

25%

  • Storm sewer pipes installed, incomplete geotech data
  • Storm video completed and submitted

50%

  • Storm sewer pipes installed, complete geotech data
  • Storm video submitted and reviewed; issues to correct from punch list generated by County or VDOT

75%

  • Storm sewer pipes CCTV submitted and reviewed by VDOT, only minor punch list items remaining (parged or adjusted without dig up required)
  • Site has achieved as-built condition related to storm sewer

100%

  • Site As-built - SAB approved
  • Storm sewer pipes SAB approved, CCTV accepted, final inspection completed
  • Trench dewatering - associated storm run installation complete
  • Storm video - No issues, if in ROW VDOT has approved

 

Reduction Percentage

Criteria

0%

  • Stormwater Facility/Facilities is acting as a temporary E&S control measure

25%

  • Stormwater Facility/Facilities installed but no 3rd party certification

50%

  • Stormwater Facility/Facilities installed with final 3rd party certification completed

75%

  • Stormwater Facility/Facilities completely installed, functioning as a whole system, site is 100% stabilized, SAB approved, final inspection has taken place with no remediation required

100%

  • Stormwater Facility/Facilities will not receive more than a 75% reduction until the final bond release to ensure no deterioration has occurred after final inspection

     

 

Reduction Percentage

Criteria

0%

  • Sanitary As-built (SAN) - not submitted, or approved
  • Sanitary trench dewatering - associated sanitary line installation not yet complete
  • Sanitary video - WCD has not TV'd the sanitary line
  • Waterline installation - not yet installed/functioning
  • Waterline trench dewatering - associated waterline installation not yet complete

25%

  • Sanitary sewer - lines and structures installed, geotech data reviewed, testing complete, no TV inspection yet

50%

  • Sanitary sewer - TV inspection complete with no outstanding punch list items

75%

  • Sanitary sewer - SAN submitted and approved, only remaining items are as-built inspection and final acceptance from WCD
  • Waterline installation - installed and functioning without final water letter

100%

  • Sanitary As-built - SAN approved
  • Sanitary sewer - final completion letter has been received from WCD
  • Sanitary trench dewatering - associated sanitary line installation complete
  • Sanitary video - WCD has TV'd the sanitary line prior to issuance of building permits for tie in
  • Waterline trench dewatering - associated waterline installation complete
  • Waterline installation - installed and final letter received from Fairfax Water

 

Reduction Percentage

Criteria

0%

  • Streetlights - not yet completely installed and operational

25%

  • Road Construction - Subbase and temporary pavement complete. Entrances installed, correct aprons. No compaction reports
  • Approved Pavement Design
  • Street Acceptance - initial package submitted and accepted

50%

  • Road Construction - Subbase and temporary pavement complete. Entrances installed, correct aprons. Correct compaction reports submitted.
  • Street Acceptance - As-built Utility package submitted and accepted

75%

  • Road Construction - Subbase and temporary pavement complete. Entrances installed, correct aprons, correct slopes, elevations, with no final inspection yet
  • Street Acceptance - Post Construction package submitted and accepted

100%

  • Road Construction - Final pavement complete, manholes adjusted, correct compaction reports submitted, final inspection of pavement and aprons completed.
  • Streetlights
    • If developer installed - installed and operational
    • If Dominion Power installed - proof of payment received
  • Street Acceptance - BOS approved and Final package submitted

 

Reduction Percentage

Criteria

0%

  • Streetlights - not yet completely installed and operational

25%

  • Road Construction - Subbase and temporary pavement complete. Entrances installed, correct aprons. No compaction reports
  • Approved Pavement Design

75%

  • Road Construction - Subbase and temporary pavement complete. Entrances installed, correct aprons, correct slopes & elevations, without final inspection completed.

100%

  • Road Construction - Final pavement complete, manholes adjusted, correct compaction reports submitted, final inspection of pavement and aprons completed.
  • Streetlights
    • If developer installed - installed and operational
    • If Dominion Power installed - proof of payment received

 

Reduction Percentage

Criteria

0 or 100%

  • Retaining Wall(s) - No reductions will be granted for retaining walls until Critical Structures has given final approval.

25%

  • Slope is at final grade, no signs of erosion, no permanent stabilization, controls still in place

50%

  • Slope at final grade, no signs of erosion, no permanent stabilization, controls removed

75%

  • Slope is at final grade, no signs of erosion, permanent stabilization, controls removed
  • Retaining Wall - is constructed, final stabilization achieved, geotechnical reports received

100%

  • Slope - Final walk completed, no erosion issues
  • Retaining Wall - final building inspection passed, final walk completed

 

Reduction Percentage

Criteria

50%

  • All landscaping installed - Landscape certification form submitted. Courtesy FCON and SDID site inspection completed during the pre-submission inspection.

100%

  • Amenities installed
  • Landscaping - final inspection at final bond release

    NOTE: All landscaping will be reinspected, and replacements may be required even if a reduction was previously granted.

 

Reduction Percentage

Criteria

0%

  • Clearing and grubbing - underway or not yet completed for entire site

25%

  • Site grading - 25% of site grading is in conformance with approved plans and revisions

50%

  • Geo tech testing and PE certifications - all third party reports and testing data submitted, subject to progress of site
  • Geo tech inspections - all third party reports and testing data submitted, subject to progress of site
  • Site grading - 50% of site grading is in conformance with approved plans and revisions
  • Test pits - site still under construction
  • Borrow fill - work is still ongoing

75%

  • Site grading - 75% of site grading is in conformance with approved plans and revisions
  • Test pits - site work completed, pending submission of final reports and tests
  • As-builts - as-builts approved
  • Borrow fill - site work completed, pending submission of final reports and tests

100%

  • Geo tech testing and PE certifications - final PE certification received, subject to progress of site
  • Geo tech inspections - final PE certification received, subject to progress of site
  • Clearing and grubbing - entire site is cleared
  • Site grading - site as-built approved and final walk through completed
  • Test pits - site work completed, all final reports and tests submitted
  • As-builts - final walk through completed
  • Borrow fill - site work completed, all final reports and tests submitted

 

Reduction Percentage

Criteria

25%

  • Rough grading and temporary stabilization - 25% of the site has seed and straw in place

50%

  • All landscaping installed
  • Erosion and sediment control measures - all work is completed, no videos, no final geo tech report for storm sewer
  • Rough grading and temporary stabilization - 50% of the site has seed and straw in place

75%

  • Rough grading and temporary stabilization - 75% or more of the site has seed and straw in place

100%

  • Erosion and sediment control measures - all work is completed, storm video completed and accepted
  • Final grading and permanent stabilization - all work completed, no erosion, no bare earth. Entire site stabilized according to DEQ standards and specifications.
  • Final landscaping inspection - completed at final bond release

 

Bond Replacements

In cases where the developer changes prior to bond release, a bond replacement package is required. If this occurs, please contact Bonds and Agreements staff at 703-222-0801, TTY 711, or via email for a replacement package relevant to your specific needs.

The new developer must follow the same procedures as a new bond. See the Bond and Permit Package for more information.

The conservation escrow is permitted to be transferred to the new developer. In cases where the developer remains but wishes to replace the current surety value, then a new supplement agreement, certificate of insurance and bond is required.

Fairfax Virtual Assistant