Public Works and Environmental Services

CONTACT INFORMATION: Our administrative offices are open 8 a.m. – 4:30 p.m., Mon - Fri
703-324-5500 TTY 711
12000 Government Center Parkway
Suite 449, Fairfax, Va 22035
Joni Calmbacher
Director, Stormwater Planning

Long Branch North at I66 Stream Restoration Project

Project No. SD-000031-266

Project Update: March 4, 2024


Project Background

The proposed restoration project is identified in the Accotink Creek Watershed Management Plan as AC9238. The existing conditions of the channels within the project area exhibit the typical degraded form resulting from many decades of development and the increase of impervious surfaces within the watershed. In November 2023, staff of the Stormwater Planning Division initiated the design of the project with consulting firm Wetland Studies and Solutions, Inc.

Severe erosion has resulted in vertical banks approximately 7 feet high.
Severe erosion has resulted in vertical banks approximately 7 feet high.

 

Channel widening exposed a utility pole, leaving it vulnerable to damage.
Channel widening exposed a utility pole, leaving it vulnerable to damage.

 

Non-native plants have taken over, suffocating all native vegetation growth. A project goal is to treat non-native species and promote a native riparian buffer.
Non-native plants have taken over, suffocating all native vegetation growth. A project goal is to treat non-native species and promote a native riparian buffer.

 

Stretches of exposed, bare banks contribute to sediment pollution during high flow events.
Stretches of exposed, bare banks contribute to sediment pollution during high flow events.

 

Project Description

The project aims to rehabilitate roughly 2,400 feet of Long Branch within the Accotink Watershed. The stream exhibits an overly down cut and widening channel, floodplain disconnection, unbalanced sediment transport, accelerated channel erosion and accelerated channel migration. There is tree loss and exposed utilities.

To accomplish this, the design plan will use Natural Channel Design (NCD) techniques. These techniques are geared towards establishing a stable channel cross-section, longitudinal profile, and planform geometry for a stream channel that is currently severely degraded. NCD works to restore a degraded stream by replicating the characteristics of a stable, natural stream. By utilizing geomorphic principles, NCD is able to achieve long-term, self-sustaining stability, even with current and future flow rates.

The primary objective of the project is to enhance water quality by revitalizing the stream and riparian corridor's ability to process phosphorous, nitrogen, and sediment. This improvement in water quality will be achieved through several means, including stabilizing the channel, installing grade control structures, connecting the floodplain, adding large woody debris to the channel bed, and planting native vegetation.

Project Location

The project is located in the Providence Magisterial District between I66 and Old Lee Hwy.

Click map to enlarge.

map - long branch providence

Project Phase

The project is in the pre-assessment phase.

Timeline

The concept plan is expected to be finalized in Fall 2024.

What to Expect

As the project advances through the iterative design development process, community meetings will be scheduled to present the project and its design to the residents along the project and to obtain feedback from the community. Meetings will be scheduled for a concept design, 95 percent design, 100 percent design/pre-construction and post-construction.

Project Cost and Funding Source

The design is funded for $590,000. Construction funding is dependent upon future budget availability and allocations. Stormwater projects are funded through the county Stormwater Service District.

Contact

For more information please email Project Manager, Vivian Bui, Stormwater Planning Division, Department of Public Works and Environmental Services, or call 703-324-5609, TTY 711.

Fairfax Virtual Assistant