Public Works and Environmental Services

CONTACT INFORMATION: Our offices are open 8 a.m. – 4:30 p.m., Mon - Fri
703-324-5500 TTY 711
12000 Government Center Parkway
Suite 449, Fairfax, Va 22035
Joni Calmbacher
Director, Stormwater Planning

Paul Spring Branch at Sherwood Hall Stream Restoration

Project Number: SD-000031-237

Project Background

channel-incision
Channel incision and widening, floodplain mowed to top of bank

The proposed stream restoration project is identified in the Little Hunting Creek Watershed Management Plan as LH9249 and LH9229. The existing conditions of the channels within the project area exhibit the typical degraded form resulting from channel evolution in response to many decades of development and the increase of impervious surfaces within the watershed: an overly down cut and widening channel, floodplain disconnection, tree loss, property loss, unbalanced sediment transport, accelerated channel erosion and accelerated channel migration.

The stream restoration design team includes County staff from Stormwater Planning Division, Maintenance and Stormwater Planning Division, Utilities Design and Construction Division, Urban and Community Forestry Division, Park Authority, Wastewater Collection Division, Land Acquisition Division, Wetland Studies and Solutions, Inc. (design engineering consultant), residents along the project area, Civic Associations and other stakeholders within the community.

Project Description

The goal of the project is to improve water quality through restoration of approximately 12,000 feet of Paul Spring Branch and the North Fork of Little Hunting Creek, tributaries, stormwater outfalls and the floodplain within the stream valley between Mason Hill Drive, Sherwood Hall Road and Collingwood Road.

The project goal will be achieved by:

  • Returning the physical characteristics of the channel to dynamic equilibrium
  • Enhancing the ecological functions and processes within the riparian corridor
  • Creating sustainable channel dimension, profile and pattern appropriate for current and future hydrologic conditions of the watershed
  • Installation of grade control structures
  • Improving floodplain connectivity
  • Stabilizing the stream bed and banks to reduce erosion
  • Installing native vegetation
  • Improving the existing floodplain wetlands
  • Enhancing the ability for biogeochemical processing of phosphorous, nitrogen and suspended sediment within the channel and on the floodplain.

Grade control structures to be installed within the stream channel will mimic bedrock outcrops and beaver dams, and may include rock sills, cross vanes, step pools, riffles, boulder riffles and large woody debris jams. These engineered grade control structures are made of boulders, clay, logs, limbs, geotextile fabric and reinforced bed material.

The stream restoration design will minimize disturbance to the existing natural resources by:

  • Using the existing footprint of the channel to the greatest extent possible
  • Realigning the channel only where necessary to protect infrastructure and to achieve the most sustainable restoration potential
  • Minimizing the limits of disturbance to the greatest extent possible
  • Preserving as many trees as possible
  • Removing trees along the channel at risk of falling into the channel due to erosion and undercut roots

Project Location

View the downloadable map. The project area is shown in red outline.

Project Phase

Pre-Design

Timeline

  • Design Start – Winter 2025    
  • Design & Permitting Completion – Late 2028
  • Construction Start – Early 2029**
  • **Please note that funding for construction is separate from authorization of design funds.  Authorization of funding for construction will be dependent on future budget allocation and prioritization**

What to expect

Community engagement efforts for the project will continue with in-person community meetings scheduled to review the existing conditions and proposed design submittals at the 35%, 65%, 95% and 100% design phases. County staff will also continue to be available to meet with Community Associations, small groups of residents, individual residents and other stakeholders to discuss the existing and proposed conditions and to best understand the community’s concerns and receive feedback on project implementation.

All community members are welcome and encouraged to participate in the project design review meetings. Additionally, a small group of volunteers from the community will be sought to work with County staff on a project Stream Team. Stream Team volunteers will be invited to attend more in-depth design development working meetings and field validation. Stream Team members will also serve as community liaisons to expand community participation and project outreach efforts through sharing design development insights with the community and providing feedback from the community to the County to help inform and shape the project implementation process. Project assessment and plan set deliverables will be made available in digital format when feasible and in physical copy in the Reference Section of the Sherwood Regional Library.

A pre-construction meeting for the community will be scheduled ahead of the Notice to Proceed being issued to the contractor, which will occur following the contractor prequalification and low-bid contract procurement process. Once construction is underway, County staff will provide thorough coordination and construction inspection on a daily basis, hold weekly progress meetings with the contractor and design/inspection staff, attend community construction progress meetings as needed/requested, offer a post-construction site walk for the community, and continue to provide project coordination and monitoring efforts to ensure success of the constructed project and installed native vegetation.

Project Cost and Funding Source

The project costs are funded by the County’s Stormwater Service District. The design task order with WSSI was approved for $1,345,000.  Funding for the construction phase of the project will be separate from the design phase and will be dependent on future budget allocations and prioritization.  The cost of construction will be determined after bids are received for construction contract authorization.

Presentations to the Community

Community Meetings for the project will be scheduled for review of design submittals and at the start and completion of construction.

Paul Spring Branch at Sherwood Hall Stream Restoration Project

Community Engagement Timeline

  • 10/10/2019 – Initial project outreach to stakeholders via email.
  • 11/19/2019 – Project introduction meeting with Hollin Hall Village Community Association.
  • 12/23/2019 – Project Introduction Letter sent to residents surrounding the project area, nearby Community Associations, Mount Vernon Council of Citizens Associations & Friends of Little Hunting Creek.
  • 1/15/2020 – Resident Meeting. Onsite. Review of existing and proposed conditions.
  • 2/24/2020 – Resident Meeting. Onsite. Review of existing and proposed conditions.
  • 6/22/2021 – Community Meeting. Online. Review existing conditions, show example projects, discuss design development process and timeline.
  • 7/1/2021 – Community Meeting. Online. Review existing conditions, show example projects, discuss design development process and timeline.
  • 7/16/2021 – Established Stream Team of residents and stakeholders for review of project design submittals and to serve as a liaison to the community.
  • 8/12/2021 – Community/Stream Team Meeting.  Review of Pre-Concept Design.
  • 9/14/2021 – Resident Meeting onsite walk with Courtland Rd residents.
  • 12/1/2021 – Community/Stream Team Meeting. Online. Review existing conditions, show example projects, discuss design development process and timeline.
  • 2/26/2022 – Community/Stream Team Meeting. Stream Team onsite walk and review of existing conditions and pre-concept design.
  • 4/15/2022 – Community Meeting with Supervisor Storck & Residents of Courtland Rd. Onsite and online.
  • 11/21/2025 – Resident Meeting. Onsite. Review existing and proposed conditions.
  • 12/5/2025 – Resident Meeting. Onsite. Review existing and proposed conditions.
  • 2/24/2026 – Community/Stream Team Meeting.  Hollin Hall Village CA. Onsite. Review of new pre-concept design.
  • 3/3/2026 – Community/Stream Team Meeting.  Stream Team. Review of new pre-concept design.
  • 3/28/2026 – Community/Stream Team Meeting.   Onsite. Stream Team. Review of new pre-concept design.
  • 4/1/2026 – Resident Meeting.  Onsite. Review existing and proposed conditions.
  • 4/7/2026 – Resident Meeting. Onsite. Review existing and proposed conditions.
  • 5/2/2026 – Resident Meeting.  Onsite. Review existing and proposed conditions.
  • 6/8/2026 – Resident Meeting.  Onsite. Stream Team. Review of new pre-concept design.
  • 6/10/2026 – Community/Stream Team Meeting.  Onsite. Review of new pre-concept design.

Contact

For more information, please email the Project Manager, Justin Pistore, at justin.pistore@fairfaxcounty.gov within the Stormwater Planning Division, Department of Public Works and Environmental Services, or call 703-324-5685, TTY 711.

Fairfax Virtual Assistant